Energía del Pacífico (EDP), one of Invenergy’s most ambitious projects, began construction in 2020, during the height of the COVID-19 pandemic.
This complex project includes a 378-megawatt combined cycle power plant, a floating storage and regasification unit (FSRU), marine infrastructure (including an underwater pipeline), and a 27-mile transmission line. Despite the enormous challenges, including supply-chain disruptions, travel restrictions, airport closures, global financial volatility, and Salvadoran COVID-19 mitigation measures and regulations, the power plant began commercial operation in October 2022.